Budget Cuts, Right-of-Way Issues Delay Major PH Transport Projects – DOTr

Several key mass transport projects in the Philippines are facing delays due to budget reductions and right-of-way challenges, according to newly appointed Department of Transportation (DOTr) Secretary Vince Dizon.

Among the affected projects are:

  • North-South Commuter Railway (NSCR) – connecting Laguna to Pampanga (27.29% complete)
  • Metro Manila Subway Project (MMSP) – running from Valenzuela to Bicutan (18.89% complete)

The government initially aimed for partial operability by 2028, but a massive 80% budget cut for foreign-assisted projects in 2025 has slowed progress. DOTr is working with the Department of Finance and the Department of Budget to secure alternative funding.

Additional Challenges & Other DOTr Plans

  • Right-of-way disputes: Legal conflicts over compensation for informal settlers along the railway route.
  • Privatization of MRT-3 and EDSA Busway by 2025.
  • Public Utility Vehicle (PUV) Modernization: Addressing concerns of traditional jeepney drivers yet to comply.
  • Cashless toll collection review: Ensuring smoother RFID integration.

Dizon assured the public that the DOTr is working to accelerate progress as directed by President Marcos.

Comments are closed for this article!

Subscribe to Our Newsletter and get a free pdf:

Sign Up for negosyante news

and receive a copy of The Crypto Cheat Sheet (PDF)
and NFT Cheat Sheet for free!

* indicates required